Gantt (Cascade) Charts (Edexcel A Level Further Maths): Revision Note

Exam code: 9FM0

Paul

Author

Paul

Last updated

Gantt charts

What is a Gantt (cascade) chart?

  • A Gantt chart - also known as a cascade chart - is a graphical display of the activities making up a project

    • a Gantt chart shows

      • the critical activities

      • the total float for non-critical activities

      • the minimum project duration

  • Gantt charts can be used in resource levelling and scheduling problems when the number of workers for each activity is known

    • in the first instance, a Gantt chart assumes one worker per activity

How do I draw a Gantt (cascade) chart?

  • (Usually) a horizontal axis is drawn for time and this appears at the top of the Gantt chart 

  • Activities are then drawn as a series of bars (rectangles) underneath

    • each activity is assumed to commence at its earliest event time

      • i.e. at the early event time of its start node 

    • each activity is assumed to occur in a single block of time

      • i.e.  no breaks!

      • e.g. an activity of duration 5 and early event time 4 would be drawn as a bar starting at 4 and ending at 9

    • Critical activities are all drawn in the same horizontal line

      • these have a total float of zero so are drawn back-to-back

    • Non-critical activities

      • are drawn one per line

      • have their total float indicated by a bar drawn with a dotted line

      • e.g. an activity of duration 4, early event time 7 and total float 3 would be drawn as a (solid) bar starting at 4 and ending at 11, with a dotted bar starting at 11 and ending at 14

    • Bars are labelled with their activity name and duration

      • floats are not labelled

  • For the activity network below

    • the critical activities are highlighted and are A, C, G and I

      • (the critical path is A-C-G-I)

    • the minimum project duration is 23 (days)

ElwVRYwN_gantt-network
  • The Gantt chart for the project would be constructed with

    • a horizontal axis running from 0 to (at least) 23

      • (0 to 25 keeps things nice!)

    • critical activities A, C, G and I drawn back-to-back on a single line underneath

    • activities B, D, E, F, H and J are each drawn on a separate line

      • e.g.  activity D will be drawn as a solid bar from 4 to 7 with a dotted bar from 7 to 12

2oXg3ddT_gantt-chart

Examiner Tips and Tricks

  • An exam question is likely to provide a grid and the axes for you to draw a Gantt chart on

  • For a non-critical activity the dotted float bar can be seen as room that the activity bar can slide back and forth along to vary it's start and end time

You've read 0 of your 5 free revision notes this week

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Paul

Author: Paul

Expertise: Maths Content Creator

Paul has taught mathematics for 20 years and has been an examiner for Edexcel for over a decade. GCSE, A level, pure, mechanics, statistics, discrete – if it’s in a Maths exam, Paul will know about it. Paul is a passionate fan of clear and colourful notes with fascinating diagrams.