Dummy Activities (Edexcel A Level Further Maths): Revision Note

Exam code: 9FM0

Paul

Author

Paul

Last updated

Dummies

What is a dummy activity?

  • A dummy activity is an activity that has a weight of zero

    • dummies are not assigned names (letters)

    • dummies are represented by dotted lines

  • Dummies are used to show precedences in more complicated activity networks

When and where are dummies used in an activity network?

  • Two situations can lead to the need for a dummy activity

  • The first situation is to ensure each activity (arc) has a unique pair of start and end nodes

    • e.g.  in the activity network below, activity D has immediate predecessors B and C

      • but B and C cannot both start at event/node 1 and end at event/node 2 (this would not be a unique pair)

      • a dummy activity is used so that B has start/end pair (1, 3) and C has start/end pair (1, 2)

dummy-sit-1
  • Note that the dummy could also go from event 2 to event 3 with activity D commencing from event 3

  • The second situation that requires a dummy is when there is a split of immediate predecessors

    • e.g.  in the activity network below, activity D has immediate predecessors B and C

      • but activity E only has B as an immediate predecessor

      • a dummy activity is used to show that D depends on both B and C

dummy-sit-2

Examiner Tips and Tricks

  • Exam questions will not always require you to draw the whole activity network

    • a diagram of part of the network may be given

  • Exam questions are often specific about the number of dummies you should use

    • if you think you need more, go back to see if you can make improvements

    • it is generally expected that an activity network is as concise/efficient as possible with the minimum use of dummies

Worked Example

The activities involved in a project are listed in the precedence table below.

Activity

Immediately preceding activities

Duration (days)

A

-

5

B

-

4

C

A

7

D

B

3

E

A, D

7

F

B

6

G

C

6

H

C

4

I

G, H

5

J

E, F

4

The project is also represented on the partially completed activity network below.

dummies-we-qu

Using exactly two dummy activities, complete the activity network by adding activities D, E, G, H, I and J.

Activity D is dependent on activity B so draw an arc from event/node 2 for D
Looking ahead, activity E is dependent on both A and D, whereas activity C is dependent on just A
This is the second situation ('split predecessors') for the use of a dummy activity
Also from looking ahead activity J depends on both E and F - so the arcs for E and F will need to meet

dummies-we-ans-1

Activities G and H are both dependent on C, and activity I is dependent on both G and H
This could lead to G and H having the same start/end node pair
This is the first situation ('unique start/end node pair') for the use of a dummy activity
No activities depend on I so its arc can be drawn to the end of the project (sink node)

dummies-we-ans-2

The activity network can now be completed with activity J and the sink node

dummies-we-final-ans

You've read 0 of your 5 free revision notes this week

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Paul

Author: Paul

Expertise: Maths Content Creator

Paul has taught mathematics for 20 years and has been an examiner for Edexcel for over a decade. GCSE, A level, pure, mechanics, statistics, discrete – if it’s in a Maths exam, Paul will know about it. Paul is a passionate fan of clear and colourful notes with fascinating diagrams.