Gantt (Cascade) Charts (Edexcel International AS Maths) : Revision Note

Paul

Author

Paul

Last updated

Gantt Charts

What is a Gantt (cascade) chart?

  • A Gantt chart is a graphical display of the activities making up a project

    • A Gantt chart shows

      • the critical activities

      • the total float for non-critical activities

      • the minimum project duration

  • Gantt charts can be used in scheduling problems 

    • A Gantt chart assumes one worker per activity

  • A Gantt chart is also known as a cascade chart

How do I draw a Gantt (cascade) chart?

  • A horizontal axis is drawn for time 

  • Activities are then drawn as a series of bars (rectangles) underneath

    • Each activity is assumed to commence at its earliest event time

      • The earliest start time is the early event time of its start node 

    • Each activity is assumed to occur in a single block of time

      • There are no breaks in an activity

      • E.g. an activity of duration 5 and early event time 4 would be drawn as a bar starting at 4 and ending at 9

  • Critical activities are all drawn in the same horizontal line

    • These have a total float of zero so are drawn back-to-back

  • Each non-critical activities is drawn on a separate line

    • Their total float is indicated by a bar drawn with a dotted line

      • The dotted float bar can be seen as the room that the activity bar can slide back and forth along

    • The start and end times of a non-critical activity are flexible

    • E.g. An activity of duration 4, early event time 7 and total float 3 would be drawn as

      • a (solid) bar starting at 4 and ending at 11 with a dotted bar starting at 11 and ending at 14

  • Bars are labelled with their activity name and duration

    • Floats are not labelled

  • For the activity network below

    • The critical activities are highlighted and are A, C, G and I

      • The critical path is A-C-G-I

    • The minimum project duration is 23 (days)

Example of an activity network
  • The Gantt chart for the project would be constructed with the following

    • A horizontal axis running from 0 to (at least) 23

      • 0 to 25 keeps things nice!

    • Critical activities A, C, G and I drawn back-to-back on a single line underneath

    • Activities B, D, E, F, H and J each drawn on a separate line

      • E.g. Activity D will be drawn as a solid bar from 4 to 7 with a dotted bar from 7 to 12

Example of a Gantt chart

Examiner Tips and Tricks

  • An exam question is likely to provide a grid and the axes for you to draw a Gantt chart on

You've read 0 of your 5 free revision notes this week

Sign up now. It’s free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Did this page help you?

Paul

Author: Paul

Expertise: Maths Content Creator (Previous)

Paul has taught mathematics for 20 years and has been an examiner for Edexcel for over a decade. GCSE, A level, pure, mechanics, statistics, discrete – if it’s in a Maths exam, Paul will know about it. Paul is a passionate fan of clear and colourful notes with fascinating diagrams.