Gantt (Cascade) Charts (Edexcel International AS Maths) : Revision Note
Gantt Charts
What is a Gantt (cascade) chart?
A Gantt chart is a graphical display of the activities making up a project
A Gantt chart shows
the critical activities
the total float for non-critical activities
the minimum project duration
Gantt charts can be used in scheduling problems
A Gantt chart assumes one worker per activity
A Gantt chart is also known as a cascade chart
How do I draw a Gantt (cascade) chart?
A horizontal axis is drawn for time
Activities are then drawn as a series of bars (rectangles) underneath
Each activity is assumed to commence at its earliest event time
The earliest start time is the early event time of its start node
Each activity is assumed to occur in a single block of time
There are no breaks in an activity
E.g. an activity of duration 5 and early event time 4 would be drawn as a bar starting at 4 and ending at 9
Critical activities are all drawn in the same horizontal line
These have a total float of zero so are drawn back-to-back
Each non-critical activities is drawn on a separate line
Their total float is indicated by a bar drawn with a dotted line
The dotted float bar can be seen as the room that the activity bar can slide back and forth along
The start and end times of a non-critical activity are flexible
E.g. An activity of duration 4, early event time 7 and total float 3 would be drawn as
a (solid) bar starting at 4 and ending at 11 with a dotted bar starting at 11 and ending at 14
Bars are labelled with their activity name and duration
Floats are not labelled
For the activity network below
The critical activities are highlighted and are A, C, G and I
The critical path is A-C-G-I
The minimum project duration is 23 (days)

The Gantt chart for the project would be constructed with the following
A horizontal axis running from 0 to (at least) 23
0 to 25 keeps things nice!
Critical activities A, C, G and I drawn back-to-back on a single line underneath
Activities B, D, E, F, H and J each drawn on a separate line
E.g. Activity D will be drawn as a solid bar from 4 to 7 with a dotted bar from 7 to 12

Examiner Tips and Tricks
An exam question is likely to provide a grid and the axes for you to draw a Gantt chart on
You've read 0 of your 5 free revision notes this week
Sign up now. It’s free!
Did this page help you?