Scheduling Activities (Edexcel International AS Maths: Decision 1): Revision Note
Exam code: XMA01
Written by: Paul
Updated on
Scheduling Activities
What is meant by scheduling (activities)?
Scheduling activities is the process of assigning workers to activities within a project
The two types of problem that arise involve
Finding the minimum number of workers such that a project can be completed in its minimum project duration
The minimum project duration is also called the critical time of the project
Finding the (new) minimum project duration given that there are constraints
E.g. There may be a maximum number of workers available at any given time
In harder problems, certain workers may only be capable of carrying out particular activities
What assumptions are made in scheduling?
In scheduling activities the following assumptions are made
Each activity requires only one worker
Or one team of workers, i.e. one resource
An activity is assigned the first available worker
If there is a choice of activities, assign a worker the activity with the lower late end time
This is the lower late event time at the activity end node
A worker can only work on one activity at a time
Once a worker has started an activity, that activity needs to be completed
How do I schedule activities for a project that requires the minimum number of workers?
For this type of problem, the critical time of the project cannot change
The critical activities cannot be delayed
One worker (resource) will complete all the critical activities
Using a Gantt chart and considering the non-critical activities
Non-critical activities can be delayed, but only within their (total) float times
Early start times can be delayed but late end times cannot
Visualise each activity as its bar being able to 'slide' within its box (solid and dotted)
Aim for as few overlaps between activities as possible
Activities can then be combined into as few rows as possible
Place them 'back-to-back'
Where possible activities should start immediately after others end
Each row on the (reduced) Gantt chart will then be completed by one worker
The number of rows is the number of workers
Remember that the precedence of activities needs to be maintained
E.g. Activity H, say, cannot move so it starts after activity I, as activity I depends on H being completed first
H is an immediate predecessor of I
What is the lower bound for the (minimum) number of workers?
The theoretical lower bound for the number of workers to complete a project in its minimum project duration is
the smallest integer value that satisfies
To find a practical lower bound for the number of workers
Imagine vertical lines drawn in between each unit
e.g. vertical lines at 0.5, 1.5, 2.5, etc
For each line, consider which activities can use their float to move so that the line does not touch them
Count the number of activities which cannot be moved and must happen at that time
The biggest number found is a lower bound
It is not always possible to schedule activities such that the lower bound can be met
How do I schedule activities for a project that has a maximum number of workers?
For a problem, where there is a maximum number of workers available at any point in time
The maximum number of workers cannot be exceeded,
It may require activities to be delayed and the project's critical time to be increased
Using a Gantt chart
Find the minimum number of workers required to complete the project in its critical time
The Gantt chart would have already been largely reduced
Do this using the process above
Consider how any activity (critical or non-critical) can be delayed
The Gantt chart must use no more rows than the (maximum) number of workers available at any time
As in the first type of problem, the precedence of activities needs to be maintained
You may want to use the activity network to check this
E.g. Activity H, say, cannot move so it starts after activity I, as activity I depends on H being completed first
H is an immediate predecessor of I
Examiner Tips and Tricks
Practise scheduling questions as exam preparation
Experience is the best way to become familiar with what to look for as there is no specific algorithm to follow
If you are asked to state a lower bound for the minimum number of workers then:
Show the calculation if you use the formula
State the time at which the maximum number of activities must happen and state those activities
E.g. A lower bound is 3 because at time 10.5 the activities A, B and F must happen
Worked Example
A precedence table and Gantt chart for a project are shown below.
Each activity requires one worker and times are given in days.
Activity | Immediately preceding activities |
A | - |
B | - |
C | A |
D | B |
E | A, D |
F | B |
G | C |
H | C |
I | G, H |
J | E, F |

a) Find the lower bound for the minimum number of workers required to complete the project within its critical time.
Answer:
The lower bound is the smallest integer greater than or equal to 2.217 ...
The lower bound for the number of workers is 3
b) Find the minimum number of workers required such that the project can be completed within its critical time.
Answer:
Worker 1 ('row 1') will be assigned to all the critical activities ('back-to-back')
Worker 2 can start activity B at time zero, with activity D following immediately (at its early start time) and activity E immediately after that

By 'sliding' activities F and H it can be seen that there will be (at least) one day where either E and F or F and H will need to happen simultaneously - therefore a third worker is needed
There is some flexibility in assigning worker 3 but activity H is dependent on activity C
Activity J is dependent on E and F but as long as F finishes by its late end time that will look after itself
The adjusted Gantt chart is

The (minimum) number of workers is the number of rows in the adjusted Gantt chart, of which there are 3
To complete the project within its critical time (23 days) a minimum of three workers will be required
c) Find the minimum project duration given that a maximum of two workers are available at any time.
Answer:
Using the solution to part b) we can see that activities A, C, B, D and E efficiently occupy two workers
Delaying activity F so it starts immediately after E will delay the whole project by one day (24 days)
(Be careful describing this, activity F would be starting after day 14, so starts on day 15)
This leaves activity H - I is dependent on it (and G) and H itself is dependent on C
Assigning H to worker 2 would delay the project by longer than necessary (at least 28 days) but by assigning H to worker 1 (either between C and G or between G and I) means precedences are maintained
The adjusted Gantt chart is

Activity I is the last to finish at a time of 27 days
The minimum project time for a maximum of two workers is 27 days
Unlock more, it's free!
Was this revision note helpful?