Activity Networks & Precedence Tables (Edexcel International A Level (IAL) Maths): Revision Note

Exam code: YMA01

Paul

Author

Paul

Last updated

Activity Networks & Precedence Tables

What is an activity network?

  • An activity network is a graph that shows the activities needed to complete a project

    • It also specifies the order in which they should be undertaken

    • E.g.  the project could be 'building a house' with activities such as 'foundations', 'walls' and 'roof'

  • Some activities will depend on others being completed first

    • E.g. the activity 'foundations' would need to be completed before the 'walls' are built

  • Some activities can occur at the same time

    • E.g. 'windows' and 'doors' can be fitted at the same time

  • The arcs (edges) of the graph represent the activities

    • This may be referred to as an activity-on-arc network

  • The nodes (vertices) of the graph represent events within the project

    • Events can be thought of as 'stepping stones'

    • The project cannot progress beyond an event until all the activities leading to that event are completed

What does an activity network look like?

  • Events (nodes) are labelled with numbers, generally increasing in the direction of the project

    • The event at the start of the project is called the source node

      • It is labelled with 0 or S

    • The event at the end of the project is called the sink node

      • It will be the highest numbered node or labelled with T

  • Arcs are labelled with their activities, with the duration given in brackets

    • Activities are denoted by capital letters - A, B, C, D, etc.

    • Arrows are drawn on the arcs to show the order in which the project progresses

      • Strictly speaking, an activity network is a directed graph

      • In broad terms, a project generally progresses from left to right across the activity network

Activity network with no dummy activities

What is a precedence table?

  • A precedence table shows a list of the activities for a project

    • For each activity, the table includes a list of the activities that must already have been completed

      • Only the immediately preceding activities are listed

    • Activities that do not have any precedents are indicated by '-'

      • These activities can begin at the start of the project

      • They will be attached to the source node

What does a precedence table look like?

  • As well as a list of activities a precedence table may also show

    • The duration of each activity

Precedence table

Drawing an Activity Network

How do I draw an activity network?

  • An activity network can be drawn from a precedence table

  • Starting with the source node

    • Add an arc for each activity one at a time

      • Consider its immediately preceding activities

    • An event (node) will be needed prior to each activity commencing

      • More than one activity can commence from the same event

      • More than one activity can finish at the same event

  • A crucial feature of an activity network is that each activity has a unique pair of start and end nodes

  • Any activities that do not precede another will go to the sink node at the end of the project

  • In general, activity networks

    • Use straight, arrowed lines for arcs

    • Numbered circles for events/nodes

Examiner Tips and Tricks

  • A rough, curly-edged activity network often helps to start off with

    • This will give you a mental picture of what the network looks like

    • You can easily make changes, scribble bits out, etc. with a rough diagram

    • When you are happy with it, you can redraw it neatly with straight edges

Worked Example

Draw an activity network for the precedence table given below.

Activity

Preceding activities

Duration

A

-

4

B

A

5

C

A

3

D

B

6

E

C

4

F

D, E

6

Starting with the source node, node 0, it is only activity A that can begin as it has no preceding activities
We will have one arc starting at the source node
Label the arc with an arrow, the activity name (A) and its duration (4)

drawact-we-ans-1

Activities B and C both depend on A
Add event (node) 1 with arcs for B and C attached
Leave plenty of room (between B and C) in case anything later needs to go in between them

drawact-we-ans-2

Activity D follows from B only, and activity E follows C only
Looking ahead though, activity F has D and E as immediate predecessors, so D and E need to meet at an event
Use event 2 to start activity D, event 3 to start activity E, and event 4 where they meet, ready for activity F

drawact-we-ans-3

Activity F is the last activity of the project so goes to the sink node, event 5

drawact-we-ans-4

Check that all activities have a unique start and end node
For example, activity B starts at event (node) 1 and ends at event (node) 2 (this may be written as an ordered pair, (1, 2))
No other activity starts at 1 AND ends at 2 (C is (1, 3))
Checking everything else, the final answer is

drawact-we-final-ans

Completing a Precedence Table

How do I complete a precedence table?

  • A precedence table can be constructed from an activity network

  • A basic table listing the activities and their duration can be constructed from the labels on the activity network

  • To complete the preceding activities column in the table

    • Start at the source node

      • Any activities starting at the source node do not have preceding activities so use '-' in the table

    • For all other activities look at the event (node) the activity starts at

      • Any activities ending at this event (node) are the immediately preceding activities

Worked Example

Construct a precedence table for the activity network shown below.

complprec-we-qu

The activities are A, B, C, D, E and F, with their durations given in brackets
Two columns of the precedence table can be completed immediately

Activity

Preceding activities

Duration

A

 

4

B

 

5

C

 

3

D

 

6

E

 

4

F

 

6

Starting at the source node 0, only activity A has no preceding activities, so this can be completed with a '-'
Work through each other activity considering the activities that go to its start event/node

  • Activity B starts at event/node 1

    • activity A ends at event/node 1

    • B has immediate predecessor A

  • C starts at 1

    • A ends at 1 

    • C has immediate predecessor A

  • D starts at 2

    • B ends at 2

    • D has immediate predecessor B

  • E starts at 3

    • C ends at 3

    • E has immediate predecessor C

  • F starts at 4

    • D and E end at 4

    • F has immediate predecessors D and E 

F is the last activity (it ends at the sink node, event 5) so the precedence table can be completed

Activity

Preceding activities

Duration

A

-

4

B

A

5

C

A

3

D

B

6

E

C

4

F

D, E

6

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Paul

Author: Paul

Expertise: Maths Content Creator

Paul has taught mathematics for 20 years and has been an examiner for Edexcel for over a decade. GCSE, A level, pure, mechanics, statistics, discrete – if it’s in a Maths exam, Paul will know about it. Paul is a passionate fan of clear and colourful notes with fascinating diagrams.