Resource Histograms (Edexcel A Level Further Maths): Revision Note
Exam code: 9FM0
Constructing a resource histogram
What is a resource histogram?
A resource histogram is a graphical way of showing the number of resources needed during each time unit (e.g. day) of a project
A 'resource' usually refers to a person (called a worker) but could refer to
a team of workers (e.g. bricklayers, roofers, painters)
a machine (e.g. cement mixer)
The number of workers needed will vary as a project progresses and will be determined by
the activities that need to happen at a particular time
the number of workers needed per activity
A resource histogram shows at a glance the maximum (and minimum) number of workers/resources needed for a project
Resource histograms can be used to help minimise the number of workers at any particular time during a project
What assumptions are made in drawing a resource histogram?
In the first instance, there are three main assumptions used in order to construct a resource histogram
Each activity begins at its earliest event time
A worker/resource can only carry out one activity at a time
Once an activity has begun, it must be completed in one go e.g. If an activity C, say, of duration 5 days, starts on day 7, it has to take place on days 7, 8, 9, 10, 11 It cannot be done on days 7, 8, 12, 13, 14 for example
Once a resource histogram is constructed, the assumptions can be reconsidered
This may be so that the number of workers/resources required at any given time is minimised
This process is called resource levelling and is covered in the next revision note
How do I draw a resource histogram?
The horizontal axis is used for time
However units of time are treated as discrete data
So "day 1" would be labelled underneath the first column
The vertical axis is used for the number of resources (number of workers)
For each unit of time
a box per worker is drawn with a label of the activity that worker is doing
multiple boxes are 'stacked' on top of each other
critical activities are at the bottom of the stack
other activities appear in alphabetical order
Each activity commences at its earliest event time
Worked Example
The Gantt chart for a project is shown below, with the duration of each activity measured in days.

The table below shows the number of workers required for each activity.
Activity | No. of workers |
A | 2 |
B | 1 |
C | 3 |
D | 2 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 2 |
J | 2 |
Construct a resource histogram for the project, assuming that each activity starts at the earliest possible time.
Activity A requires 2 workers and lasts for 5 days

Add the rest of the critical activities with their number of workers

Other activities can be added in order
Activity B is straightforward but activity D gets 'bumped' up for days 6 and 7 days due to activity C requiring 3 workers (whilst activity A only needed 2 workers)

Add the other activities carefully, one at a time, considering where any are 'bumped' up or down

It is always worth double checking - especially any 'bumped' activities - and check the minimum duration time (23 days)

Unlock more, it's free!
Did this page help you?