Venn Diagrams & Tree Diagrams (AQA Level 3 Mathematical Studies (Core Maths): Paper 2B: Critical Path & Risk Analysis): Revision Note

Exam code: 1350

Naomi C

Written by: Naomi C

Reviewed by: Dan Finlay

Updated on

Guided study available on this topic

Understand this topic with deeper explanations and understanding checks.

Venn Diagrams

What is a Venn diagram?

  • A Venn diagram is a way to illustrate events from an experiment and are particularly useful when there is an overlap (or lack of) between possible outcomes

  • A Venn diagram consists of

    • A rectangle representing the sample space

    • A circle for each event

      • Circles may or may not overlap depending on which outcomes are shared between events

How are Venn diagrams labelled and what do the numbers inside mean?

  • The rectangle represents the sample space (all possible outcomes from the experiment)

    • It is often referred to as the Universal Set and is commonly labelled with S, U, ξ (the Greek lower case letter Xi) or E(Kunstler script font)
      There is no standardised symbol used for this purpose

  • Circles are labelled with their event name (A, B, etc.)

  • The numbers inside a Venn diagram (there should be one in each region) will represent either a frequency or a probability

    • In the case of probabilities being shown, all values should total 1

Two Venn diagrams with two overlapping sets A and B. The first diagram shows the frequencies in the different sections of the diagram whilst the second diagram shows the probabilities of those different sections of the diagram.

What do the different regions and bubbles overlapping mean on a Venn diagram?

  • This will depend on how many events there are and how the outcomes overlap

  • Venn diagrams show ‘AND’ and ‘OR’ statements easily

  • Venn diagrams also instantly show mutually exclusive events

    • Independence can be deduced from the probabilities involved

Four separate Venn diagrams with two overlapping sets A and B. The first diagram highlights the regions of the diagram that represent event A. The second diagram highlights the regions that represent not A. The third diagram highlights the regions of the diagram that represent A or B or both. The fourth diagram highlights the regions of the graph that represent neither A nor B.
Two Venn diagrams. The first diagram shows two sets A and B, when B is a subset of A. The second diagram shows three sets A, B and C, with A and B overlapping and B and C overlapping but there being no overlap between sets A and C.

How do I solve probability problems involving Venn diagrams?

  • Draw, or add to a given Venn diagram, filling in as many values as possible from the information provided in the question

  • It is usually helpful to work from the centre outwards

    • I.e. fill in intersections (overlaps) first

    • This is particularly crucial with Venn diagrams with three events

      • If all three circles overlap, the intersection of events A and B  will include the intersection of events A, B  and C

      • A question would make it clear if a given frequency or probability is only for events A and B , and not C

  • Any frequencies or probabilities not given may be able to be calculated from those that are

    • Use the results from basic probability to deduce missing frequencies or probabilities and answer questions

  • Check a completed Venn diagram that the frequencies sum to the total involved or that probabilities sum to 1

Examiner Tips and Tricks

Always draw the box in a Venn diagram; it represents all possible outcomes of the experiment so is a crucial part of the diagram.

In complicated problems it can be helpful to draw a “mini-Venn” diagram for part of a question and shade/label the regions of the diagram that are relevant to that part.

Worked Example

40 people were surveyed regarding which games consoles they owned.

  • 8 people said they owned a Playbox (P) and an X-Game (X)

  • 11 people said they owned a Playbox (P) and a Ninjado (N)

  • 7 people said they owned an X-Game (X) and a Ninjado (N)

  • 4 people said they owned none of these consoles

  • 2 people said they owned all 3

Of those people that owned only one games console:

  • Twice as many owned a Ninjado as a Playbox,

  • and half as many owned an X-Game as a Playbox.

(a) Draw a complete Venn diagram to illustrate the information given above.

Answer:

Draw an initial Venn diagram

Starting from the central point of intersection, 2 people said they owned all 3

8 people said they owned a Playbox and an X-Game, so the number of people who owned a Playbox and an X-Game but not a Ninjado is

8 - 2 = 6

11 people said they owned a Playbox and a Ninjado, so the number of people who owned a Playbox and a Ninjado but not an X-Game is

11 - 2 = 9

7 people said they owned a Ninjado and n X-Game, so the number of people who owned a Ninjado and an X-Game but not a Playbox is

7 - 2 = 5

Let the number of people who own an X-Game only be x
Then the number of people with a Playbox only would be 2x and the number with a Ninjado only would be 4x

The number who owned no consoles is 4, so that number can be written outside the circles but within the rectangle

Venn diagram with three overlapping sets P, N and X.

Set up an equation to find x

2x+6+x+9+2+5+4x+4=407x+26=40x=2

Now draw the complete Venn diagram

Venn diagram with three overlapping sets P, N and X, with all sections completed with the final values.

(b) One of the 40 people is chosen at random. Find the probability that this person,

Answer:

Sketch a mini Venn diagram to illustrate the section required for each part 

(i) owns all three consoles,

Venn diagram with three overlapping circles. The intersection of all three circles is shaded.

P(P and X and N)=240

P(P∩X∩N)=120

(ii) owns exactly two consoles,

Venn diagram with three overlapping circles. The intersection between each pair of circles is shaded but the intersection of all three circles is not shaded.

P((P and X) or (P and N) or (X and N))=640+940+540=2040

P((P∩X)∪(P∩N)∪(X∩N))=12

(iii) doesn’t own a Playbox.

Venn diagram with three overlapping circles. The whole diagram is shaded with the exception of the top left circle.

P(P')=1−P(P)=1−4+6+9+240=1−2140

P(P')=1920

(c) Determine if the events X and N are independent.

Answer:

If A and B are independent then P(A and B)=P(A)×P(B)

From the Venn diagram

P(X)=6+2+2+540=1540P(N)=9+2+5+840=2440P(X and N)=2+540=740

P(X)×P(N)=1540×2440=940

P(X and N)≠P(X)×P(N),
therefore the events X and N are not independent

Tree Diagrams

What is a tree diagram?

  • A tree diagram is used to

    • Show the (combined) outcomes of more than one event that happen one after the other

    • Help calculate probabilities when AND and/or ORs are involved

  • Tree diagrams are mostly used when there are only two mutually exclusive outcomes of interest

    • E.g. “Rolling a 6 on a dice” and “Not rolling a 6 on a dice”

  • More than three outcomes per event can be shown on a tree diagram but they soon become difficult to draw and so lose their effectiveness

  • Tree diagrams are very helpful when probabilities for a second event change depending on the first event

How do I draw and label a tree diagram?

A tree diagram showing two experiments each with two possible outcomes.
  • In the second experiment, P(B)  may be different on the top set of branches than the bottom set

    • This is because the top set of branches follow on from event A but the bottom set of branches follow on from event "not A"

    • E.g. If a red ball is taken from a bag and not replaced in the first experiment, then the probability of picking a red ball in the second experiment has now changed

  • Sometimes a second branch may not be needed following a first event

    • E.g. In aiming to pass a test, the event fail on the first attempt would require a second attempt but the event pass on the first attempt would not

A tree diagram for passing a test, where no 2nd attempt is required if first attempt is passed. Only one pair of branches on 2nd attempt.

How do I solve probability problems involving tree diagrams?

  • Interpret questions in terms of AND and/or OR

  • Draw, or complete a given, tree diagram

    • Determine any missing probabilities

      • Use 1−P(A)

      • Consider if probabilities for the 2nd experiment change depending on the outcome from the 1st experiment

  • Write down the (final) outcome of the combined events and work out their probabilities

    • These are AND statements

    • P(A and B)=P(A)×P(B)

      • Do not simplify fractions yet

  • If more than one (final) outcome is required to answer a question then add their probabilities

    • These are OR statements

    • P(AB or A'B')=P(AB)+P(A'B') 

      • This applies since all the (final) outcomes are mutually exclusive

      • Note that AB and A'B' are implied AND statements (for example AB means  A and B)

Examiner Tips and Tricks

  • Tree diagrams have built-in checks

    • The probabilities for each pair of branches should add up to 1

    • The probabilities for each outcome of combined events should add up to 1

  • Remember the AND and OR rules

    • Multiply along branches (AND)

    • Add down the list of final outcomes (OR)

Worked Example

A contestant on a game show has three attempts to hit a target in a shooting game in order to win the star prize – a speedboat.  If they do not hit the target within three attempts, they do not win anything.

The probability of them hitting the target first time is 0.2.  With each successive attempt the probability of them failing to hit the target is halved.

Find the probability that a contestant wins the star prize of a speedboat.

Answer:

Draw a tree diagram and determine the missing probabilities

H is the event "hits target"
M is the event "misses target"

Tree diagram of three separate experiments each with two outcomes, hit or miss.

Read along the branches, write down the outcome and work out its probability

Method 1

P(wins speedboat)= P(H) + P(MH) + P(MMH) = 0.2 + 0.48 + 0.256 = 0.936

P(wins speedboat) = 0.936

Method 2

P(wins speedboat)= 1 - P(MMM) = 1 - 0.064

P(wins speedboat) = 0.936

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Build on this topic

Naomi C

Author: Naomi C

Expertise: Maths Content Creator

Naomi graduated from Durham University in 2007 with a Masters degree in Civil Engineering. She has taught Mathematics in the UK, Malaysia and Switzerland covering GCSE, IGCSE, A-Level and IB. She particularly enjoys applying Mathematics to real life and endeavours to bring creativity to the content she creates.

Dan Finlay

Reviewer: Dan Finlay

Expertise: Portfolio Lead

Dan graduated from the University of Oxford with a First class degree in mathematics. As well as teaching maths for over 8 years, Dan has marked a range of exams for Edexcel, tutored students and taught A Level Accounting. Dan has a keen interest in statistics and probability and their real-life applications.