Types of Costs (Cambridge (CIE) A Level Accounting): Revision Note

Exam code: 9706

Seina Murakami

Written by: Seina Murakami

Reviewed by: Dan Finlay

Updated on

Direct & indirect costs

How are material and labour costs accounted for?

  • Material and labour costs are accounted so they can be included in the cost of production

  • Accounting for material costs involves:

    • Recording purchases and usage of inventory

    • Allocating direct material costs to production costs

    • Allocating indirect material costs to overheads

  • Accounting for labour costs involves: 

    • Recording wages 

    • Allocating direct labour costs to production 

    • Allocating indirect labour costs to overheads

What is a direct cost?

  • Direct costs are those that can be specifically associated with the manufacture of one unit of production

  • Examples include:

    • Direct materials 

    • Direct labour 

    • Other direct costs

      • E.g. royalties

How are direct costs calculated?

  • Direct material and labour costs are calculated by multiplying the rate per unit by the quantity used 

    • Direct materials cost = Cost per unit ×Units used

      • Unit could be kg, litres, metres etc.

    • Direct labour cost = Cost per hour ×Hours used

  • Other direct costs are also included in direct costs 

    • E.g. royalties costed $200, so include $200 in direct costs 

Worked Example

Product A requires 2 metres of fabric and 6 hours of labour to manufacture.

Each metre of fabric is $4 and the wage rate per hour is $8.

Royalty cost is $3 per unit.

Calculate the direct cost per unit.

Answer:

Direct materials:

2m × $4 per m = $8 per unit

Direct labour

6 hours × $8 per hour = $48 per unit

Other direct costs (royalties): $3 per unit

Direct cost = Direct materials + Direct labour + Other direct costs

8 + 48 + 3 = 59

$59 per unit

What are indirect costs?

  • Indirect costs are those that cannot economically be specifically associated with the manufacture of one unit of production

  • Indirect costs are also known as overheads and can be classified as

    • production overheads

      • Production overheads are included in production costs 

    • administrative overheads

    • or sales and distribution overheads 

      • Administrative overheads and sales and distribution overheads are included in total costs but not production costs 

  • Examples include:

    • Depreciation of machinery 

    • Electricity 

    • Rent of factory 

    • Maintenance costs

Examiner Tips and Tricks

Direct costs are often variable costs, while indirect costs are often fixed costs.

Remembering this can help when classifying costs.

How are indirect costs calculated?

  • Indirect costs are often divided into a factory portion and an administrative portion using specified allocation percentages

    • The factory portion is included in production cost

    • While the administrative portion is not included in production cost

  • Indirect cost included in production cost = Indirect cost × Allocation percentage

Worked Example

Rent and rates was $125 000 for the year ended 31 December 2024.

Rent and rates are to be allocated 60% to the factory and 40% to the office.

Calculate the amount of rent and rates to be included in production cost.

Answer:

125 000 × 60% = 75 000

Add $75 000 to direct costs and this will be the production cost.

Fixed, variable, semi-variable & stepped costs

What are fixed costs?

  • Fixed costs are costs that remain unchanged within a certain level of activity/output

    • E.g. depreciation of machinery  

What are variable costs?

  • Variable costs are costs that are constant per unit

  • Total variable cost increases as output increases

    • E.g. direct material costs

How can fixed costs and variable costs be calculated? 

  • Use the high-low method

  • STEP 1

    Identify periods with higher and lower activity level 

  • STEP 2

    Calculate the variable cost per unit

    Variable cost per unit = (Higher activity total cost  Lower activity total cost)(Higher output units  Lower output units)

  • STEP 3

    Calculate the fixed cost

    Fixed cost = Higher activity total cost  (Variable cost per unit x Higher output units)

    OR

    Fixed cost = Lower activity total cost  (Variable cost per unit x Lower output units)

Worked Example

Total cost at 1 000 units = $8 000 

Total cost at 600 units = $6 400 

Calculate the variable cost per unit and fixed costs.

Answer:

STEP 1

  • Higher activity level = 1 000 units at $8 000 

  • Lower activity level = 600 units at $6 400 

STEP 2

  • Variable cost per unit is

(8 000 - 6 400) ÷ (1 000 - 600) = $4 per unit 

STEP 3

  • Fixed cost

8 000 - (4 × 1 000) = $4 000 

  • Or fixed cost

6 400 - (4 × 600) = 4 000

Variable cost is $4 per unit

Fixed cost is $4 000

What are semi-variable costs?

  • Semi-variable costs are costs that are partly fixed and partly affected by production level

  • For example, electricity is a semi-variable cost

    • Fixed: Standing charge 

    • Variable: Cost per unit of electricity used 

How can semi-variable costs be calculated? 

  • Use the high-low method

  • STEP 1
    Identify periods with higher and lower activity level

  • STEP 2
    Find the variable cost per unit

    • Variable cost per unit = (Higher activity total cost  Lower activity total cost)(Higher output units  Lower output units)

  • STEP 3
    Find the fixed costs

    • Fixed cost = Higher activity total cost  (Variable cost per unit × Higher output units)

    • Or Fixed cost = Lower activity total cost  (Variable cost per unit × Lower output units)

  • STEP 4
    Write it as a formula

    • Semivariable cost = Fixed costs + (Variable cost per unit × Number of units)

What are stepped costs?

  • Stepped costs are fixed for a given level of activity and increases when that level is exceeded

  • For example, factory rent is a stepped cost 

    • Rent is fixed for one space but increases when an additional space is rented 

How can stepped costs be calculated?

  • From identifying ranges: 

  • STEP 1

    Identify the ranges and the relevant costs for these ranges

  • STEP 2

    Add the relevant costs together

Worked Example

Supervisor cost: 

1 supervisor is required for every 20 workers. 

Each supervisor has a salary of $2 000

What is the supervisor cost for 35 workers? 

Answer:

Number of steps required:

35÷20 = 1.75

Round up to 2 supervisors

2 × $2 000 = $4 000 

Total supervisor cost is $4 000

How types of costs change depending on level of activity
Types of costs

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Seina Murakami

Author: Seina Murakami

Expertise: Accounting Content Creator

Seina studied Pharmacology at UCL, though her professional passion lies deeply in the world of accounting and finance. With an A* in CIE A-Level Accounting and extensive experience tutoring IGCSE and IAL students, she specializes in making complex financial concepts accessible. From developing comprehensive revision resources to collaborating with faculty on lesson materials, Seina is dedicated to helping students bridge the gap between struggling with content and mastering it.

Dan Finlay

Reviewer: Dan Finlay

Expertise: Portfolio Lead

Dan graduated from the University of Oxford with a First class degree in mathematics. As well as teaching maths for over 8 years, Dan has marked a range of exams for Edexcel, tutored students and taught A Level Accounting. Dan has a keen interest in statistics and probability and their real-life applications.