10.3 Implementing Strategy (AQA A Level Business): Flashcards

Exam code: 7132

1/32

0Still learning

Know0

Cards in this collection (32)

  • Define strategic implementation.

    Strategic implementation is the process of putting strategic plans into effect — turning objectives into day-to-day operations.

  • What two key factors does effective implementation depend on?

    Strong leadership and clear communication.

  • Name two roles leaders play in implementation.

    Vision setting and decision-making (also change management, empowering others and role modelling).

  • Give one risk of weak leadership in implementation.

    Confusion over priorities (also low engagement/resistance, missed deadlines and wasted resources).

  • Why is communication important in strategic implementation?

    It clarifies goals, motivates staff, reduces resistance and coordinates actions across departments.

  • Name two key elements of strategic communication.

    Clarity and consistency (also timeliness, two-way communication and channel selection).

  • Why is two-way communication valuable in implementation?

    It allows feedback, questions and suggestions to be heard and addressed.

  • Give one internal communication tool for implementing strategy.

    Team meetings (also internal email, intranet/portals, workshops and 1-to-1 reviews).

  • Why does organisational structure matter for implementation?

    It provides clear roles/responsibilities, efficient communication and decisions, and better coordination and control.

  • What does vision setting involve for a leader?

    Articulating a clear, inspiring vision that aligns with the business's strategic aims.

  • Even the best strategy can fail without strong leadership and clear   .

    Even the best strategy can fail without strong leadership and clear communication.

  • True or False?

    Strategic implementation is simply about choosing the right strategy.

    False.

    It is about turning the chosen strategy into action — day-to-day operations that deliver results.

  • True or False?

    A flat organisational structure can speed up decision-making during implementation.

    True.

    Fewer management layers allow faster decisions and clearer communication — as seen at Aldi.

  • Define network analysis.

    Network analysis is a project management tool for planning complex, time-sensitive strategies.

  • Give two things network analysis shows.

    The order of activities and the shortest time to complete the project (also EST/LFT, critical activities and float).

  • Give one limitation of network analysis.

    Complex projects need specialist software; it relies on estimates/forecasts and doesn't guarantee success.

  • Define a node (network diagram).

    A node is a circle representing a point in time where an activity starts or finishes.

  • What three sections is a node split into?

    The activity number (left), the earliest start time (top right) and the latest finish time (bottom right).

  • What is the earliest start time (EST)?

    The earliest an activity can begin, based on completion of the previous activity.

  • How do you calculate earliest start times (ESTs)?

    Work forwards from Node 1, adding each activity's duration.

  • How do you calculate latest finish times (LFTs)?

    Work backwards from the final node, subtracting each activity's duration.

  • A node can be reached by paths giving 14 and 15. Which EST is recorded?

    15 — the highest value, so all preceding activities can be completed first.

  • Define the critical path.

    The critical path is the activities that determine the length of the whole project — if any is delayed, the project is delayed.

  • How do you identify the critical path on a diagram?

    Follow the nodes where the EST and LFT are equal (float = 0).

  • Define float time.

    Float time is the spare time available for an activity without delaying overall project completion.

  • State the formula for total float.

    Total float = LFT − duration − EST.

  • An activity has LFT 11, duration 4, EST 6. Calculate its total float.

    11 − 4 − 6 = 1 week.

  • What is the total float of activities on the critical path?

    Zero — there is no spare time on critical activities.

  • What can happen to the critical path if a non-critical activity's duration increases enough?

    The critical path can switch — e.g. from BEH to ADG when activity G's duration rises.

  • The critical path follows the nodes where the EST and LFT are   .

    The critical path follows the nodes where the EST and LFT are equal.

  • True or False?

    Activities on the critical path have a float of zero.

    True.

    Critical activities have no spare time — any delay to them delays the whole project.

  • True or False?

    If a critical activity is delayed, only that activity is affected, not the whole project.

    False.

    A delay to a critical activity delays the whole project.