Critical Path Analysis (Edexcel A Level Business): Revision Note

Exam code: 9BS0

Lisa Eades

Written by: Lisa Eades

Reviewed by: Steve Vorster

Updated on

The nature and purpose of critical path analysis

  • Critical path analysis is a project management tool that uses network analysis to plan complex and time-sensitive projects 

  • It involves the construction of a visual model of the project that includes key elements:

    • A list of all activities required to complete the project

    • The time (duration) that each activity will take to complete

    • How each project activity depends on others

  • Critical path analysis shows:

    • The order in which activities must be completed

    • The longest path of project activities to the completion of the project

    • The earliest and latest that each project activity can start and finish without delaying completion of the project as a whole

    • Activities within a project that can be carried out simultaneously

    • The critical project activities that, if delayed, will cause the project as a whole to overrun

    • Those project activities where some delay is acceptable without delaying the project as a whole

    • The shortest time possible to complete the project

  • It allows managers to identify the relationships between the activities involved and to work out the most efficient way of completing the project

    • Resources such as raw materials and components can be ordered or hired at precisely the right time they are needed

    • Working capital may be managed efficiently

    • Where delays occur, managers can identify the implications for the project’s completion and redirect resources if required 

Drawing critical path analysis diagrams

Components of network analysis diagrams

Element

Description

Node

  • A node is a circle that represents a point in time where an activity is started or finished

  • The node is split into three sections

  • The left half of the circle is the activity number 

  • The top right section shows the earliest start time (EST) that an activity can begin based on the completion of the previous activity

  • The bottom right section shows the latest finish time (LFT) by which the previous activity must be completed

Activities

  • An activity is a process or task within a project that takes time

  • Activities are shown on the network diagram as a line that links nodes 

  • A description of the activity or a letter representing the activity is usually shown above the line

Duration

  • The duration is the length of time it takes to complete an activity

  • The duration is shown as a number of time units, such as hours or days, below the activity line

Example network diagram

Flowchart diagram illustrating a project schedule with nodes, activities, durations, earliest start time (EST), and latest finish time (LFT).
A simple network diagram showing key elements: node, activity and duration
  • A network diagram must always start and end at a single node

  • Lines must not cross and must only be assigned to activities

Critical path calculations

Earliest start times

Network diagram with circles A to H connected by lines. Each circle contains two numbers; lines are labelled with single-digit numbers.
An example of a simple network diagram showing earliest start times
  • Working forwards from Node 1, it is possible to calculate the earliest start time (EST) for each activity by adding the duration of each task

  • The EST for each activity is placed in the top right of each node

    • Node 1 is the starting point of the project and where both Activity A and Activity B begin

    • Activity A and Activity B are independent processes

    • Activity A has a duration of two days, and its EST is zero days

    • Activity B has a duration of three days, and its EST is also zero days

    • Activity C and Activity D both begin at Node 2 and are dependent upon the completion of Activity A but are independent from each other

      • Activity C has a duration of three days, and its EST is two days 

      • Activity D has a duration of five days, and its EST is also two days

    • Activity E begins at Node 3

      • Activity E has a duration of four days, and its EST is three days

    • Activity F begins at Node 4

      • Activity F has a duration of two days, and its EST is five days

    • Activity G begins at Node 5

      • Activity G has a duration of one day, and its EST is seven days

    • Activity H begins at Node 6

      • Activity H has a duration of three days, and its EST is seven days

    • Node 7 is the endpoint of the project

Latest finish times

Network graph with nodes labelled A to H and numbered 0 to 7. Lines show connections and weights between nodes. Nodes have multiple values inside circles.
An example of a simple network diagram showing ESTs and LFTs
  • Working backwards from Node 7, it is now possible to calculate the latest finish time (LFT) for each activity by subtracting the duration of each task

  • The LFT for each activity is placed in the bottom right of each node

    • Node 7 is the endpoint of the project, which has an LFT of ten days

    • Activity H has a duration of three days

      • The LFT in Node 6 is seven days (10 days − 3 days)

    • Activity G has a duration of one day

      • The LFT in Node 5 is nine days (10 days − 1 day)

    • Activity F has a duration of two days

      • The LFT in Node 4 is eight days (10 days − 2 days)

    • Activity E has a duration of four days

      • The LFT in Node 3 is three days (7 days − 4 days)

    • Activity D has a duration of five days

      • The LFT in Node 2 is four days (9 days − 5 days)

    • Activity C has a duration of three days

      • The LFT in Node 3 is four days because Activity D is the more time-critical of the two activities that are dependent upon the completion of Activity A, so its LFT is recorded

    • Activity B has a duration of three days

      • The LFT in Node 1 is zero days (3 days − 3 days)

    • Activity A has a duration of two days

      • The LFT in Node 1 is zero days because Activity B is the more time-critical of the two starting activities, so its LFT is recorded

  • The LFT in Node 1 is always zero

Identifying the critical path

  • The critical path highlights those activities that determine the length of the whole project

    • If any of these critical activities are delayed, the project as a whole will be delayed

    • The critical path follows the nodes where the EST and LFT are equal

      • In the diagram below, Nodes 1, 3, 6 and 7 have equal ESTs and LFTs

      • Activities that determine these nodes are B, E and H

      • These activities are marked with two short lines

      • The critical path is therefore BEH

Network flow diagram with nodes A to H, each with capacity and flow. Arcs include values like A-2, C-4, and B-3, with paths marked in red and blue lines. The critical path is red.
An example of a simple network diagram showing the critical path, BEH

Identifying and calculating float time

  • Float time exists where there is a difference between the EST and the LFT

  • Where float time is identified, managers may:

    • Transfer resources, such as staff or machinery, to more critical activities

    • Allow extra time to complete tasks to improve quality or allow for creativity

Network diagram showing nodes with calculations and notes on differences at nodes 4, 5, and 6. Includes paths A-H and float time information.
An example of a simple network diagram showing float nodes (4 and 5) and a critical node (6)
  • The total float refers specifically to the spare time that is available so that the overall project completion is not delayed

  • The total float for a specific activity is calculated using the formula

LFT for the activity − Duration of the activity − EST for the activity

  • Using the diagram above, the following total float times can be calculated for Activities A to H

Activity

LFT

- Duration

- EST

= Total float

A

4

2

0

2

B

3

3

0

0

C

8

3

2

3

D

9

5

2

2

E

7

4

3

0

F

10

2

5

3

G

10

1

7

2

H

10

3

7

0

  • The critical activities B, E and H each have a total float of zero days

Worked Example

The network diagram below shows the activities involved in a new promotional campaign for a small fashion accessories business, as well as the time (in weeks) it is expected that each activity will take to complete.

A network diagram with nodes 1 to 8 and activities A to J, used to calculate earliest start times, latest finish times and float

Calculate:

a) The ESTs and LFTs for each node  [4]

b) The total float time for Activity G  [3]

Step 1: Calculate the ESTs

Node 1 EST = 0

Node 2 EST = 0 + 3 = 3, but 0 + 4 = 4 so 4

Node 3 EST = 4 + 5 = 9

Node 4 EST = 4 + 2 = 6

Node 5 EST = 9 + 3 = 12

Node 6 EST = 6 + 4 = 10

Node 7 EST = 4 + 6 = 10

Node 8 EST = 12 + 2 = 14, but 10 + 4 = 14, and 10 + 5 = 15, so 15 [2]

Step 2: Calculate the LFTs

Node 8 = 15

Node 7 = 15 − 5 = 10

Node 6 = 15 − 4 = 11

Node 5 = 15 − 2 = 13

Node 4 = 11 − 4 = 7

Node 3 = 13 − 3 = 10

Node 2 = 10 − 6 = 4

Node 1 = 4 − 4 = 0 [2]

Step 3: Calculate the total float time for Activity G

Total float  =   LFT for the activity  −   Duration of the activity    −   EST for the activity   =    11 weeks    −   4 weeks    −   6 weeks  =    1 week [3]

Limitations of using critical path analysis

Limitations

Explanation

Very lengthy or complex projects involve a very large number of activities that have numerous dependencies

  • Specialist network planning software may be required

  • Layers of supervision may be required to manage different groups of activities within the project

Network analysis often relies on estimates and forecasts

  • Significant research is required prior to the completion of network analysis

  • Close and honest working relationships with suppliers are essential

Network analysis does not guarantee the success of a project 

  • Project managers will need to be highly skilled and will need experience working with complicated plans

Resources may not prove to be as flexible as hoped when managers identify float periods

  • Employees may require additional training in order to transfer to critical tasks

  • Machinery and other capital resources may require adaptation

Unlock more, it's free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Build on this topic

Lisa Eades

Author: Lisa Eades

Expertise: Curriculum Expert

Lisa has taught A Level, GCSE, BTEC and IBDP Business for over 20 years and is a senior Examiner for Edexcel. Lisa has been a successful Head of Department in Kent and has offered private Business tuition to students across the UK. Lisa loves to create imaginative and accessible resources which engage learners and build their passion for the subject.

Steve Vorster

Reviewer: Steve Vorster

Expertise: Content Creator

Steve has taught A Level, GCSE, IGCSE Business and Economics - as well as IBDP Economics and Business Management. He is an IBDP Examiner and IGCSE textbook author. His students regularly achieve 90-100% in their final exams. Steve has been the Assistant Head of Sixth Form for a school in Devon, and Head of Economics at the world's largest International school in Singapore. He loves to create resources which speed up student learning and are easily accessible by all.